Cherni Vrah Blvd. was put into operation ahead of schedule

Publish date 28 November 2016
Cherni Vrah Blvd. was put into operation ahead of schedule image

Sofia's Cherni Vrah Boulevard has been launched ahead of schedule.

Reconstruction of the boulevard began in July 2016. The renovated road section is 1.4 km long with two lanes with 2 lanes in each direction and another for a left turn at the intersections. The cost of the repairs and expansion is BGN 13 million. Cars will now be able to run on the section. The buses with numbers 64, 98 and 122 will travel on their routes.

The Sofia Municipality warns that the repair works on the sidewalks continue.